Everything was set for the coming weekend of November 4, 2016. The cement was all cured, so we ordered all of the necessary lumber, sheeting, house wrap, trusses,… you know, house building supplies. We met the delivery truck at the property.
The day was bright and clear, making for a good start for the walls! We were all very excited for this day, for we had waited and waited to begin building. Adam’s father Don, his brother Benjamin, our friend George, & our good friends Abe & Samantha came to help. Little did we know then that Abe had purposed in his heart to help us the entire way. They came up to Crandon every weekend we were working, until we were ready for the rough in electrical & plumbing! They are amazing friends!!
We got a lot done that first day.
This is the south side of the house. The washroom doorway is at the end of the wall there, with Adam & I’s bathroom window next to it.